KCD:NOC actual
April 2010:
The Project Interim Report was approved by the Financial Mechanism Office in Brussels, as the FMO informed on the 28th of April 2010.
The Public Procurement was launched by the Central Procurement Organisation at the
Ministry of Culture of the Slovak Republic on the 21st of April 2010.
March 2010:
The following organisations have accepted the offer of cooperation on the KCD:NOC Project: the Slovak National Museum, the Centre for Folk Art Production and the Monuments Board of the Slovak republic.
February 2010:
The Preliminary announcement of the Public Procurement for the KCD:NOC Project was published by the the Central Procurement Organisation at the Ministry of Culture of the Slovak Republic on the 16th of February, 2010
November 2009:
the Project Management Team was appointed as following:
- Project manager
- Administration Manager
- Finance Manager
- Publicity Manager
- Procurement Manager
- IS Manager
- KCD:NOC Principal
The project team meetings take place weekly. The external consultant for EEA and Norway grants is assisting the project team in monitoring the implementation.
The National Culture centre as the Project Promoter is implementing the first activity – summarizing the objects of cultural heritage for digitalisation.
The following types of objects are being prepared:
- paper documents
- large format documents
- 2D objects
- 3D objects
- audio objects
- video objects
- architectural objects
October 2009:
Grant Agreement signed between the National Focal Point – The Government Office of the Slovak republic and the Project Promoter – The National Culture Centre.